Electric Panel Build - IN PROCESS - PART 1

Getting Started

Measure twice, cut once



Greenlee hole punch


Be Patient


The Guts

Originally I was going to build a 120V system with plans to upgrade to 220V down the road.






I switched gears and decided to opt for a 50A system with DIN rails

src="https://c6.staticflickr.com/8/7645/28163825765_b33f301507_z.jpg" width="640" />


 


Beginning to take shape



Basement Work Station



Switched to Back to Back system now, relocated switch and added yellow LED for corresponding PID (heating Element)


  

Heating Elements from THEELECTRICBREWERY.COM
These will be housed in the HLT and BK
There is already a RIMS unit fully built and ready for power wire to be attached.


 

Element Enclosures
Brewhardware.com

 


It's time to start cleaning up the Keezer

UPGRADE: prepping for a new Keezer Facia 

 I acquired this from the local home depot in the clearance rack, I believe I'll be able to make this $10 look great!

 

Starting to take shape